Transformer tap changers adjust the winding turns ratio to change the output voltage. The two main operating categories are on-load tap changers (OLTC) and de-energized tap changers (DETC). Their key difference is whether the tap position can be changed while the transformer remains energized.
An OLTC is designed to change winding taps while the transformer is energized and carrying load. Its switching arrangement transfers current between taps under controlled conditions. This allows voltage regulation as supply conditions and demand change.
OLTCs are used where operating conditions require repeated voltage adjustment without taking the transformer out of service, including many substation applications. The control system, tap range and switching duty must match the transformer design.
On-load tap changers can be classified as resistor or reactor types according to their transition arrangement. Both belong to the OLTC category. This classification is separate from the main distinction between on-load and de-energized operation.
A DETC changes the selected winding tap only when the transformer is de-energized. It is often described as an off-circuit or no-load tap changer, but the term no-load must not be interpreted as permission to operate it while the transformer remains energized.
DETCs are used in power and distribution transformers where tap changes are infrequent and an outage can be arranged. They can be found in substation, pad-mounted and pole-mounted transformer designs.
| Selection point | OLTC | DETC |
|---|---|---|
| Operating condition | Designed for energized, on-load switching | Transformer must be de-energized |
| Typical duty | Voltage regulation during operation | Infrequent adjustment during an outage |
| Switching arrangement | Includes provisions for switching load current | Does not switch energized load current |
| Selection basis | Tap range, through-current, switching duty and control | Tap range, current rating, mounting and access |
Provide the transformer drawing, winding arrangement, required tap positions, electrical ratings, operating duty and mounting dimensions. Selection should follow the transformer design and the tap changer manufacturer’s instructions.
Tap changers regulate voltage; transformer bushings provide insulated conductor connections through the tank. The two components perform different functions.
No. It requires the transformer to be de-energized and the specified isolation procedure to be completed.
OCTC means off-circuit tap changer, and NLTC means no-load tap changer. These names commonly refer to de-energized tap-changing arrangements. Always follow the equipment instructions: removing the load alone does not make energized tap changing permissible.
The correct type depends on whether tap changes are needed during operation or only during an outage.